SEL Posted August 15, 2018 Share Posted August 15, 2018 We are working on a large masterplan with a number of different buildings on site. WE are going to build each of the block in a separate file and reference them into a 'Master' Site plan. However, as the site has overall a 5m height difference across its length, the buildings will be 'stepped', i.e. they won't all have the same 0.00 level. but hey will be staggered, to meet the existing contours. My question is how, once referenced inc an I decided the equivalent 0.00 point for each building (which would the be the actual Datum given by a topographic survey.) I cannot seem to find an answer anywhere but I am sure its a problem many have encountered. Thanks in advance. Quote Link to comment
AlanW Posted August 17, 2018 Share Posted August 17, 2018 @SELHi,once referenced in on site plan which would have a height of zero you can move all the models (originally drawn at Zero RL) up to desired RL. You can hold curser on the top of the slab and the RL will show in bottom right of screen to be able to check. 1 Quote Link to comment
Recommended Posts
Join the conversation
You can post now and register later. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.